greentec steel Linz
voestalpine · Linz · AT · Steel · circularity
In construction
greentec steel Linz is voestalpine's steel project at Linz, Austria.
Why it matters
It is being built.
- greentec steel Linz went into construction on 18 June 2026. as of 2026-06-18
- It is at Linz, Austria. as of 2026-06-18
- It uses electric arc furnace on scrap. as of 2026-06-18
- No committed public money is on file for it. as of 2026-06-18
Where greentec steel Linz is
greentec steel Linz is at Linz steelworks. Also in frame: 1 site using the same technology.
filled: operating, commissioning or under constructionhollow: announced, funded, or pausedringed: this project
48.2785° N 14.3196° ELinz steelworks
as of 2026-06-18
Status
- Announced
- Funded
- FID taken
- In construction2026-06-18
- 2026-06-18In constructionThe same release states the first phase covers both Austrian sites at an unchanged investment of about EUR 1.5 billion, with an electric furnace at each going into operation from 2027.source
Technology and measures
- Electric arc furnace on scrapcommercialSteel is remelted from scrap in an electric furnace, with no ironmaking step and therefore none of its CO2. It is not an emerging route — it is already two fifths of European output — and what limits it is how much scrap of the right quality Europe collects and keeps, not whether the furnace works.
Funding
No public capital recorded for this project.
Sources
- voestalpine unveils further expansion plans for greentec steel at its Donawitz locationvoestalpine · 2026-06-18