Tranmere and Stanlow terminal
Stanlow Terminals (Essar Energy Transition) · Tranmere and Stanlow · GB · Carbon capture and fuels · decarbonisation
Tranmere and Stanlow terminal is Stanlow Terminals (Essar Energy Transition)'s carbon capture and storage project at Tranmere and Stanlow, United Kingdom.
Why it matters
Nothing has been committed to it yet.
- Tranmere and Stanlow terminal was announced on 8 August 2023. as of 2023-08-08
- Its site is at Tranmere and Stanlow, United Kingdom. as of 2023-08-08
- It uses CO2 transport and storage. as of 2023-08-08
- No committed public money is on file for it. as of 2023-08-08
Where Tranmere and Stanlow terminal is
Tranmere and Stanlow terminal is at Tranmere and Stanlow, United Kingdom, and this register holds no position for it. The company has confirmed the site and no citable source places the works: it is being built where nobody has yet drawn it. The row is held anyway — position is not a condition of being on file — and what was searched, and what was found instead, is below.
NO POSITION SOUGHT BY THIS PASS. Brief 8 forbids geocoding in a census — a municipality is not a point — and the source that admits this row names Tranmere and Stanlow and not a position. Transport and storage is the sector where that bites hardest: a pipeline is a route rather than a place, and a store is a reservoir whose position its operator rarely publishes. The row is admitted without one, on the rule that position is not an admission leg.
Status
- Announced2023-08-08
- Funded
- FID taken
- In construction
- 2023-08-08AnnouncedStanlow Terminals (Essar Energy Transition), own site: “The proposed terminal will play a critical role in enabling carbon capture, utilisation and storage (CCUS) infrastructure by facilitating the import and handling of CO2.”source
Technology and measures
- CO2 transport and storageearly-commercialThe pipelines, ships, terminals and permitted geological stores that a captured tonne has to reach before it counts as abated, and which no single site that captures can build for itself.
Funding
No public capital recorded for this project.
Sources
- Tranmere and Stanlow terminalStanlow Terminals (Essar Energy Transition) · 2023-08-08