CycloneCC Rudersdorf is CEMEX's cement project at Ruedersdorf, Germany.
Why it matters
Nothing has been committed to it yet.
- CycloneCC Rudersdorf was announced on 19 July 2022. as of 2022-07-19
- Its site is at Ruedersdorf, Germany. as of 2022-07-19
- It uses post-combustion carbon capture. as of 2022-07-19
- No committed public money is on file for it. as of 2022-07-19
Where CycloneCC Rudersdorf is
CycloneCC Rudersdorf is at Ruedersdorf, Germany, and this register holds no position for it. The company has confirmed the site and no citable source places the works: it is being built where nobody has yet drawn it. The row is held anyway — position is not a condition of being on file — and what was searched, and what was found instead, is below.
NO POSITION SOUGHT BY THIS PASS. Brief 8 forbids geocoding in a census -- a municipality is not a point -- and the owner statement that admits this row names the works and not a position. The works is Ruedersdorf. A polygon for it is a separate job and the row is admitted without one, on the rule that position is not an admission leg.
Status
- Announced2022-07-19
- Funded
- FID taken
- In construction
- 2022-07-19AnnouncedCarbon Clean, the technology partner, naming CEMEX and the works: “KBR will provide FEED services for the initial stage of the project which aims to develop and deploy Carbon Clean's breakthrough modular carbon capture technology - CycloneCC - to initially capture 100 tonnes per day (TPD) of CO2 at the plant”source
Technology and measures
- Post-combustion carbon captureearly-commercialCO2 is separated from the kiln's flue gas after combustion, using an amine or solvent process bolted onto an existing plant, which is what makes it the retrofit route for kilns that are not being rebuilt.
Funding
No public capital recorded for this project.
Sources
- CycloneCC RudersdorfCarbon Clean · 2022-07-19