CO2LLECT
CEMEX · Ruedersdorf · DE · Cement and concrete · decarbonisation
CO2LLECT is CEMEX's cement project at Ruedersdorf, Germany.
Why it matters
Nothing has been committed to it yet.
- CO2LLECT was announced by 14 September 2026. as of by 2026-09-14
- Its site is at Ruedersdorf, Germany. as of by 2026-09-14
- It uses post-combustion carbon capture. as of by 2026-09-14
- No committed public money is on file for it. as of by 2026-09-14
Where CO2LLECT is
CO2LLECT is at Ruedersdorf, Germany, and this register holds no position for it. The company has confirmed the site and no citable source places the works: it is being built where nobody has yet drawn it. The row is held anyway — position is not a condition of being on file — and what was searched, and what was found instead, is below.
NO POSITION SOUGHT BY THIS PASS. Brief 8 forbids geocoding in a census -- a municipality is not a point -- and the owner statement that admits this row names the works and not a position. The works is Ruedersdorf. A polygon for it is a separate job and the row is admitted without one, on the rule that position is not an admission leg.
Status
- Announcedby 2026-09-14
- Funded
- FID taken
- In construction
- by 2026-09-14AnnouncedCO2LLECT, the project's own site (CEMEX and Linde): “The new plant aims to capture, liquefy and purify around 1.3 million tons of CO2 from cement production every year”source
Technology and measures
- Post-combustion carbon captureearly-commercialCO2 is separated from the kiln's flue gas after combustion, using an amine or solvent process bolted onto an existing plant, which is what makes it the retrofit route for kilns that are not being rebuilt.
Funding
No public capital recorded for this project.
Sources
- CO2LLECTCO2LLECT · by 2026-09-14